It’s been less than a year since the Lester and Sue Smith Legacy Tower opened its doors for the first time to care for our most critically ill patients at Texas Children’s Medical Center campus. And, in that short period of time, Texas Children’s has made great strides for our patients and their families.
On May 22, 2018, Smith Legacy Tower opened with 45 critically ill patients. Four months later on September 25, Texas Children’s No. 1 ranked Heart Center opened in Smith Legacy Tower to deliver care to 64 patients. Since that historic moment, Texas Children’s critical care, cardiology, surgical and radiology teams have been busy.
To date, Smith Legacy Tower has had 3,870 patient admissions in the pediatric and cardiac intensive care units. More than 5,000 patients have received care at Smith Legacy Tower’s outpatient Heart Center clinics, and over 450 catheterization and 476 MRI procedures have been performed in the new tower.
A total of 2,356 surgeries were completed in Smith Legacy Tower’s state-of-the-art surgical and cardiovascular operating rooms, totaling 9,495 surgical hours. In the first three months of opening the tower’s new helipad, Texas Children’s had 66 helipad landings, allowing for even greater access to Texas Children’s for the sickest patients.
“I don’t know of any other children’s hospital in the country that has the type of experience that Texas Children’s has in bringing all of these elements together,” said Texas Children’s Surgeon-in-Chief Dr. Larry Hollier. “With Legacy Tower providing much larger, more functional spaces for our patients, clinical and surgical teams, we are delivering on our promise to ensure every child receives the right care, at the right time and in the right place.”
West Tower Backfill Project
Following the successful opening of Smith Legacy Tower, construction is now underway to backfill and renovate the patient care spaces on floors 7 and 15 of West Tower that were left vacant from the patient moves.
Part of the West Tower Backfill project involves transitioning patient care services out of the Abercrombie Building which currently serves as Texas Children’s general pediatrics and pediatrics hospital unit. As one of the hospital’s oldest facilities, the smaller spaces and limited technological capabilities have historically presented challenges for providers, clinical care teams, patients and their families.
“When our executive steering committee was formed to look at space planning and space management for our clinical programs, one of our guiding principles was to decrease or eliminate care in Abercrombie,” said Assistant Vice President of Nursing Jennifer Sanders. “As our patients and staff become more dependent on technology, there are challenges due to the age of the facility.”
7 West Tower
As part of the backfill project, 7 West Tower will become a 32-bed dedicated hematology and oncology unit that will include 22 hematology-oncology rooms and 10 bone marrow transplant rooms.
Formerly known as the Progressive Care Unit, several patient rooms had been set up as pods where four patients occupied one room. Construction is underway to reconfigure this space into four private rooms. Renovations will also include a multi-disciplinary work area, larger family lounge and respite areas.
Cancer and hematology patients from other parts of West Tower and Abercrombie will move to 7 West Tower once renovation is completed. The targeted date of completion is September 2019.
15 West Tower
While 15 West Tower used to be Texas Children’s cardiovascular intensive care unit, this space will be redesigned to meet the future growth of our acute care patient population.
By converting this space from critical care to acute care, 15 West Tower will become a 36-bed acute care Pediatric Hospital Medicine (PHM) unit that will include a family lounge and respite spaces. The unit will include four behavioral health rooms, multi-disciplinary work area and space for our PHM providers.
Patients from Abercrombie 5 and 6 will move to 15 West Tower, and during this transition, 7 South Abercrombie will be a “patient ready” floor that will serve as an acute care unit during high patient census. The targeted date of completion is July 2019.
6 West Tower
The last component of the West Tower Backfill project is the reconfiguration of 6 West Tower that will address different patient populations on one floor. Expected to be completed in late 2020, 6 West Tower will become a separate inpatient and outpatient dialysis and pheresis unit. While this floor used to house the administrative offices for critical care physicians, the hospital’s neonatology offices are still located there.
“Collaborating with our facility planning and development partners, our nursing team has played a crucial role in leading the West Tower Backfill project,” said Associate Chief Nursing Officer Jackie Ward. “The patient move from Abercrombie to West Tower will help us meet the future growth of acute care, while enabling our patient care teams to collaborate more efficiently in these new, enhanced spaces. This change will also enhance and improve our patient and staff experience.”